Friday, March 25, 2016

Mar 25, 2016 Annex Update

The roof is going on today or anyway the trusses went on today.



The North end round  beams have been installed also.
And looking toward the East you can kind
of see the retaining wall for the steps descending 
from the Bean Museum parking lot.





Thursday, March 24, 2016

Mar 24, 2016 BYU Annex Update

Progress continues to be steady on the iron work framing. 


 The pouring of the last 1st level floor was delayed due to rain and snow.



Today (24th) however the floor was poured.


 and iron work continued at the same time.





The bell tower also appears to be getting an exterior facelift.

 All the cement was in and just the finish work on it left as I 
finished work today.

Monday, March 21, 2016

March 16-20, 2016 Annex Update

So it has been a few days since I have been able to post an update.
The floor has been poured for the court.



There are a number of the beams that are now installed.



The walls of the stairs are completed.




Gravel for the remaining floor is now in and 
the blue plastic barrier installed.













 The beams for the floor of the second floor 
have mostly been installed .

Round beams for the South East corner are in.