Friday, January 29, 2016

BYU Annex Jan 29, 2016 update

Sometimes things seem to happen a little faster. 
Now that they are putting the roof on the tunnel
there are some quick changes.













Wednesday, January 27, 2016

Jan 27, 2016 Annex update


Walls being poured.


 Ground being leveled and compacted

 Steps? to where?

More fill dirt being brought to the site.




Soon there will be enough dirt in this side.

Starting to form the roof for the tunnel.

Tuesday, January 26, 2016

Annex Update, ground levels rising

They are filling in the dirt around the stair well now.
Each time some is taken in then it is compacted.


 It sure looks slow though for these 
forms being put together.

It also looks like the retaining walls for the
sidewalk are nearing completion.







 Installing the remaining parts of the drain line
for these two parts of the ground.




 Drains in and ground covered over agin.



Sunday, January 24, 2016

Jan 22, 2016 Annex update

Drain pipes have been installed and soon they will
back fill the dirt into this area.



Another part of the footings and walls are being
formed over by the tunnel.

Backfill starting for the first part.