Saturday, April 2, 2016

Mar 31, 2016 Annex Update

More of the roofing has been put up


There were only a few of the bolts
originally installed while the iron was first
being raised now they have been going
back and adding the rest to the structure.

And welding the seams together also.

The southwest steel is also not being completed.

Bell Tower facelift also continuing

Last side of the East steps being poured

Wednesday, March 30, 2016

Mar. 30, 2016 Annex Update

More iron is on and today they started 
putting the sub-roofing on.











Monday, March 28, 2016

Mar 28, 2016 Annex Update


The steel work continues.

 There was only one set of cross bars between the trusses
and today they added more


 It is looking pretty good but there is still a lot of steel to go up.