Thursday, March 10, 2016

March 10, 2016 Annex Update

It was fun today to go and see that they were putting
in the rebar for the floor and had poured the steps
this morning.





Tuesday, March 8, 2016

BYU Annex update

They are getting the floor ready to pour cement
 and a lot of the plumbing is nearing completion.





Sunday, March 6, 2016

New trail cam subject matter, a cat.

I have moved the old picnic table off the pavilion
and found the neighborhood cat loves to sit on it.










 Watching the deer leaving this morning.


 Selfie

Saturday, March 5, 2016

Mar 5, 2016 Annex Update

(Did not work today so it is just more from what they had done yesterday.)



Friday, March 4, 2016

Mar 4, 2016 Annex update

Just a few images from today.



Putting tar one the outside of the wall. 



I am not sure why they made another 
crossover point for trucks.
Will find out later I am sure.

Thursday, March 3, 2016

Mar 3, 2016 Annex update

Well a few more things are happening.
Stairs are formed.

 More pipes laid under the floor to be.



 The ground once again leveled and compressed.



Wednesday, March 2, 2016

Mar 2, 2016 Annex Update


The east stairs starting to be framed


The most fun it seems for us is to guess at how many times
they are going to move the dirt from one place to another.





 Adding boards for steps.

Various views of the building's footprint.



Boards in place now they are adding rebar.