Friday, April 15, 2016
April 15,2016 Annex update
Windows inside completed with doors.
I went down these stairs today and the
old lobby on the East was pretty dark
with no windows for light.
The walls are starting to look pretty filled in on the
East, North and South
Thursday, April 14, 2016
Apr. 14, 2016 Annex update
Drywall on east almost up
Drywall on North side being installed
remaining metal added to west side today
window crew at work inside the Marriott on the concourse
Apr. 13, 2016 Annex update
More drywall and stairwell enclosure
outside door in, inside area started to be removed
Apr. 12, 2016 Annex update
Tuesday progress more drywall,
outside walls for stairs installed
Apr 11, 2016 Annex Update
A week away from BYU and the Annex made some
advances in the progress.
Notice the walls and drywall changes over the next 4 days as well.
The inside door from concourse to the stairs is also going together.
‹
›